Well things are really moving along. This week we were able to prepare the forms to pour the concrete footer for the retaining wall. On Friday, we rented a large, diesel powered concrete mixer and poured the footer. We had a great turnout then, with 15 total people present so everything went smoothly like a well-oiled machine. The neatest thing was that all of us are Brethren in Christ Church members, so working alongside so many brothers within the church halfway across the world is such a huge encouragement.

We will start this week laying the brick to build the retaining wall. The BIC Malawi General Conference is coming up in a couple of weeks, so it would be great to have the wall built before then, along with having the entire work site completely leveled and compacted. Thanks all for your support. Please continue to pray for the BIC Church of Malawi - for the people and for their project. There is so much potential for this project and for the general church in so many ways.