Below are some pictures of the continued progress on the Maone Ministry Center. Reports from Malawi indicate that the walls and superstructure will soon be to the point where the roof will be ready to be installed. Materials and supplies of course will be needed and there are plans underway to see a team from the USA come in July to help raise the roof. Things are challenging however as the Kwacha continues to lose strength and thereby making local items rise higher and higher in cost.
Just a reminder that the BIC Church purchased a cement mixer to help with the project rather than constantly renting one which has proved to be a great addition to the effort.
Great news too, there have been no accidents on the work site given the heights the workers are working at. It is rainy season now so the rains can affect working conditions too.
Thanks everyone for your interest and support.